Project Updates
Current projects can be found on our website at Smithville, MO

Maintenance Updates

  • Parks
    • Maintenance completed 2 water leaks in the campground
    • Mowed all parks
    • Painted sports fields
    • Preparing new park signage
  • Streets
    •  Fixed mailbox at 200 Commercial Ave
    •  Graded dirt at Wildflower outflow pond
    •  Fixed manhole riser 1004 Aspen Dr in Forest Oaks
    • Graded 134th St. for dust control 
    • Marcus Road cut for patch work 
    • Mowed DD Hwy
    • Filled potholes with millings on Park Dr
    • Backfilled approach for the parking lot on W. Meadow St
    • Started road base repair along 176th St to Thomas Ln
  • Utilities
    • Total Drinking Water Production 9,192,000 gal
    • Completed all testing required at the WTP
    • Conducted weekly chemical level checks at the WTP for ordering
    • Backwashed filters 1,2,3,4 and 5 at the WTP
    • Finished painting the handrails around the filters at the WTP
    • Replaced the chlorite feed line in the chemical building
    • Replaced the pump head for the ACH chemical pump
    • Replaced the exhaust fan belt in the filter room at the WTP
    • Completed grounds maintenance at the towers and booster stations
    • Completed 20 work orders
    • 75 locates completed
    • Completed all testing required at WWTP
    • Treated 4,523,000 gallons of wastewater
    • Completed weekly checks of all booster station and towers in the distribution system
    • Collected and delivered 3 E-coli samples to the KCMO laboratory
    • Completed grounds maintenance at the WWTP and WTP
    • Ace completed lining manholes for the 2026 CIPP project
    • Replaced the effluent valve for SBR#2 and set limit switches on SBR#1 influent valve
    • Hauled and land applied 11 loads of sludge from digestor #1
    • Repaired a water main break on Raintree Lane